By utilizing the “slot cut” installation method temporary shoring was eliminated that would have been requires for other wall types.  Therefore the overall wall cost and construction time was greatly reduced compared to other wall options.

Area Noveco Inc. Client Cut Wall w/o shoring Scope Of Work
9SO
Counterforts set in "slots" cut into existing embankment

Counterforts set in “slots” cut into existing embankment

2SO 4SO 5SO 12SO